LOCAL ROAD CLOSURES FEBRUARY - MARCH (UPDATED2)
Balfour Beatty Living Places have issued their updated programme of road works for February and March. These include the following which may affect some Bodenham residents:
HIGHWAY RESURFACING WORKS – ROAD CLOSURES
Resurfacing works (including white lining and stud works, if required) as well as any preparatory works (i.e. drainage, kerbing) if required.
A417 – Hillhampton to Burley Gate Wednesday, 24 March 2021 to (and including) Wednesday, 31 March 2021 Road closed 09.00 hours to 17.00 hours daily No weekend working.
DRAINAGE WORKS
Excavation of carriageway as part of improvements to the local drainage system:-
U94017 – Maund Common Lane, Bodenham Monday, 22 February 2021 to (and including) Friday, 12 March 2021 Full 24/7 closure: Road closed from 09.00 hours on 22 February 2021 and does not re-open until 17.00 hours on Friday, 12 March 2021.
Please note that the programme can change at any time, and sometimes at very short notice, so please keep an eye on Twitter@HfdsStreets for all latest updates. Alternatively, please visit https://one.network/ as this shows all road works currently in place on the network, whether this be traffic lights or road closures.
Date: 29/01/2021
|